There is no wetlands permit for the Marcy "Nano" site because Local Leaders chose that route.
Back on 12/11/2002, a "Concerned Citizen" wrote to local officials on this very issue:
[Prior and followup e-mails are here and here]
A few days ago I wrote to you to express my concern that Oneida County might be losing an opportunity to land a chip-fab plant at the site in Marcy. Today an article in the Utica O-D revealed that Mohawk Valley EDGE's permit application for the site faced rejection by the U.S. Army Corps of Engineers (ACOE), that EDGE officials applied for the permit Oct. 29, 2001, and that EDGE will now wait until it finds a developer before it resubmits the application.
Oneida County for months has represented the Marcy site as "shovel-ready" for computer chip fabrication. "Shovel-ready" (according to the "Semi-NY" website, one place where the Marcy site is advertised) means that "no permitting obstacles stand in a company 's way" and that the site will be "available for groundbreaking within 60-90 days."
Today's article begs the question: Is our site "shovel-ready" or not? The fact that EDGE's application to ACOE has been pending for over a year with still no approval suggests that it is not.
In light of the County's advertisements on the "Semi-NY" and MVEdge websites, today's OD article makes it appear that the County has been distributing misleading information. Why is the County indicating that its site is "shovel ready" when it has no permit from ACOE and has known for well over a year that it needed a permit? Can Oneida County assure prospective tenants that the site will be available for groundbreaking within 60-90 days? Should prospective businesses rely on the information that Oneida County provides?
Putting aside the issue of the County's credibility, why is the County giving up pursuing the ACOE permit NOW? Is ACOE saying that the County has no right to provide a "shovel-ready" site? I doubt it: ACOE cannot forbid without qualification any encroachment on the wetlands without effectively condemning the property. Given that we have a Republican County Executive, a Republican Congressman (one of the most senior members in the House), a Republican President, and, perhaps most important, a Republican Governor who has been pushing the Semi-NY "shovel-ready" concept, it is incredible that Oneida County does not have the "clout" to cut through the federal red-tape. Did the County bother to ask for help?
These questions need to be answered.
As I indicated in my last letter, Oneida County's big advantage in seeking a chip-fab is having a site ready NOW. When other sites closer to Albany come on line, it will be difficult for us to compete.
The County needs to resolve the ACOE permit issue, and pursue chip-fab companies, NOW.
Amazingly, among the multitude of recipients of the above e-mail, only Mrs. Destito had the courtesy to respond regarding the concern over the lack of an ACOE permit. After acknowledging that the points raised in the e-mail were valid, she stated:
However, I do agree with the decision of the Mohawk Valley EDGE officials to wait until a specific business expresses an interest in the area to apply for the Army Corps of Engineers site permit. . .Mrs. Destito's letter confirms that shelving the permit application was "the decision of the Mohawk Valley EDGE officials."
There is no wetlands permit for the Marcy "Nano" site because Local Leaders chose that route.