Thursday, August 26, 2021

Deconstruction of Another Fact Check: Death Rates for Vaccinated vs Unvaccinated for a Covid Variant.

covid 19, coronavirus, covid, cell, pandemic, corona virus, organism, water, plant, fungus, Free Images In PxHere

 This is another Reuters' "Fact-Check" that I happened to run across while researching something else:

"Fact Check-Claim that vaccinated people are six times more likely to die from the Delta variant than those who are unvaccinated is misleading"

"Social media posts have claimed that those who have received a COVID-19 vaccine are more [sic] six times more likely to die from being infected by variants than those who have not been inoculated. While the data was indeed taken from a Public Health England (PHE) briefing held in June, it was taken out of context."

Reuters then links to several blog posts that make the claim. (Follow the links provided in Reuters' fact-check if you want to read the original claims -- two are provided in the last section of this post below.)

Unlike the last Reuters fact-check reviewed in this blog, this time Reuters fairly characterized the "six times" claim in the blog posts

However, like the last fact-check reviewed, Reuters, again, confirmed all the salient data in the blog posts. In particular ... 

"Referring to data compiled by Public Health England (PHE) in a technical briefing released on June 18 regarding the SARS-CoV-2 variants (here), the authors of the blogs make several calculations.

 "On page 12 of the briefing, it shows that 26 people have died since February 1 after testing positive for the Delta variant of the virus, having also been fully vaccinated for more than two weeks. In total, 4,087 tested positive more than two weeks after their second dose. Meanwhile, 35,521 people who were unvaccinated tested positive for the Delta variant and 34 people died.

"The authors then divide the number of deaths by the total number of people who tested positive for the Delta variant and found the rate of death to be 0.000957 for unvaccinated individuals and 0.00636 for those who have been inoculated."

Reuters does not claim that the source data is wrong.  Nor does it claim that the mathematical calculations are wrong. You can check the math yourself. Nothing is wrong with it. 

A DELTA VARIANT DEATH RATE OF 0.00636 FOR VACCINATED PEOPLE IS INDEED BETWEEN 6 AND 7 TIMES THE  DELTA VARIANT DEATH RATE OF 0.000957 FOR UNVACCINATED PEOPLE.

Math is a form of logic. (Some call it "critical thinking.") Since the math is correct, and the data is correct, then the conclusion reached (as restated above) based upon that data has to be both logical and correct.  

What does Reuters say?

"The logic is flawed, however, and PHE told Reuters that two doses of the vaccine has shown “high levels” of protection against the Delta variant....

"“The analysis presented is very misleading and ignores the fact that deaths predominantly occur in older age groups who have had much higher vaccination coverage,” Prof Paul Hunter, Professor in Medicine at Norwich Medical School told Reuters over email . . . 

""The figures in the blog posts lack context, Dr Muge Cevik, clinical lecturer in infectious diseases and medical virology at the University of St Andrews, told Reuters by email. . . .

"“When most people are vaccinated, most infections and deaths are expected to be among those vaccinated,” she added.

"The vaccination program also prioritised [sic]“clinically vulnerable” individuals, and thus the majority of those vaccinated will “disproportionately represent elderly and those with underlying comorbidities, who are already at significant risk of hospitalisation and death,” Dr Cevik, said. ...

"The overall rate of infection is much less in vaccinated populations, which “indicates that vaccination is working,” Dr Shamaila Anwar, science communicator with Team Halo, told Reuters ..."

Reuters also has several other people making comments on various aspects of the vaccination program, and reaches its ultimate:

        "VERDICT 

"Missing context. Vaccinated people are not at higher risk of dying from the Delta variant than those who are unvaccinated . . ." 

If you read all the statements Reuters presents to make its case, NONE of them state that "Vaccinated people are not at a higher risk of dying from the Delta variant than those who are unvaccinated." 

Fault Line's Verdict on the Reuters Fact-Check: FALSE.  

Basically Reuters is trying to compare Apples to Oranges and does not really address the issue. Although Reuters implies that older ages of the persons in the study could have lead to a faulty conclusion, Reuters failed to present any alternative data and/or calculations to demonstrate that a different conclusion on the risk of death for vaccinated vs unvaccinated could be reached.

Reuters entirely failed to present any evidence to support the factual assertion made in its so-called "verdict." 

Since Reuters cited no flaw in the Bloggers' math, nor any flaw in the data cited, and since Reuters failed to produce its own evidence to directly refute the Bloggers' calculations, Reuters statement that the Bloggers were "Missing Context" is false.

Why is this important?

The two main blog posts cited and archived by Reuters, "DC Clothesline," and  "Lifesite" both raise a question whether or not the higher risk of death for vaccinated persons for the Delta variant is evidence that Antibody Dependent Enhancement (ADE) is occurring. Per Lifesite, "ADE blighted previous attempts at coronavirus vaccines and frequently resulted in enhanced lung disease among vaccinated lab animals" and "led researchers in 2012 to advise scientists to proceed with “caution” for any human coronavirus vaccines which could lead to enhanced lung disease." Lifesite also indicated that ADE could "activate other sleeping infections in the vaccinated person such as herpes virus, creating symptoms of Bell’s palsy or shingles" and might even "accelerate the rate at which the vaccine-resistant mutant strains become dominant among all the SARS-Co-V2 [coronavirus] strains.” 

The Reuters "Fact-Check" failed to even mention let alone address these concerns. If ADE is occurring, it would mean that the vaccine could actually be causing harm. Any "fact-check" on this issue really needs to address the ADE issue.




Sunday, February 28, 2021

Deconstruction of a "Fact Check" --- or "Fact-checking a Fact-Checker"

Are "Fact Checkers" reliable, or are they no better than those they are "fact-checking?" 

A friend sent me the following article:  Elderly population suddenly dying off for unexplained reasons, and it’s no longer coded as covid-19 – NaturalNews.com

Per the article:

"Around the world, medical authorities are seeing a spike in elderly deaths, after covid-19 vaccination. Gibraltar, a nation located at the southern tip of Spain, is suffering from an unexplained surge in elderly deaths. In the second week of January, a subset of the elderly population suddenly started to die off. ...

"Before the vaccine experiment began, the covid-19 related death toll accounted for ten people. After the vaccine rollout, the total number of deaths had skyrocketed to forty-five people. In the first eight days of the vaccination program, thirty-five seniors suddenly passed away.".

Not familiar with "NaturalNews.com" I did a search of what for me were the key elements of the story: a surge in deaths following the Covid vaccine in Gibraltar.  I eventually found this article in Reuters

Fact check: Vaccine not linked to COVID-19 deaths in Gibraltar.  Per the article: 

"The claim that coronavirus deaths in Gibraltar have been caused by the vaccine, not the virus, has been shared on social media. This claim is false."

Reuters then linked to two Facebook posts (which had the Facebook "False Information" flag attached) and recited the offending language:

“Gibraltar is 2.6 square miles in size. On 6th January they had only 10 covid deaths in total. The vaccine arrived to the island on 10th January. By 20th of January there were 53 deaths. Today worldometer is showing that there are now 70 deaths. SEVENTY!! Why is no one talking about Gibraltar?”

Observation 1: Reuters misconstrued the social media posts

 Do you see a claim in the quote above that the vaccine caused the deaths? It's not there!

Observation 2:  Reuters confirmed all the salient information in the social media posts while claiming them to be false.

Specifically it confirmed that the vaccine program had begun in Gibraltar on January 10, 2021, that as of that date 16 Covid deaths had been record, that by the 20th the deaths had increased to 53, and that 7 days later they had increased to 70.

Observation 3: Reuters then falsely claimed "But there is no evidence whatsoever that these deaths are linked to the roll out of the vaccine." 

But there IS evidence: the close following of the surge in deaths to the commencement of the vaccine program links the two together in time. Although this evidence is clearly insufficient to prove a causal relationship, it WAS sufficient to both cause (1) the social media posts and (2) Reuters to read into the social media posts a statement of causal relationship that was not there. 

Observation 4: Reuters then offers, without evidence, two alternative theories to explain the surge in deaths.

Reuters states that "The increase appears to be part of an upward trend that started before the first vaccine dose was administered." After lying to us three times, why should we accept this claim without any data to support it? None is presented. 

Reuters goes on to allege that per government officials, 6 people "appear to have caught Covid-19 before they were vaccinated ... Despite testing for COVID-19 before vaccination, the infection had not been detected in them at the time they were vaccinated, but in the days immediately after.”  The "appearance" of an infection before the vaccination is a speculative opinion, not a fact.

Observation 5: The Reuters headline "Vaccine not linked to Covid-19 Deaths in Gibraltar" is deliberately misleading because it can be read in two different ways

(1) The vaccine did not cause the deaths in Gibraltar; or (2) No one has proven a link between the Deaths and the Vaccine. The first is unproven. The second only has meaning if a diligent search for a connection had been made -- which is not in evidence.

Verdict on the Reuters Fact Check: FALSE.  

The fact-check, by what is usually considered to be a reliable news source, contains three lies, presents alternative theories without evidence, and presents a misleading headline.  The social media posts, which merely cite undisputed facts that prompted a question, are more credible!

(Because the Fact Check confirmed a surge in deaths following the vaccine rollout in Gibraltar, it tended to support some of what was in the Natural News article that initially piqued my interest.)

Monday, January 11, 2021

Capitol Riot: Connect These Dots -- and Tell Me what you Think

1) Capitol Police: "[T]he responsibility of policing the Capitol [is] under the direction of the presiding officer of the House and Senate" 

2) Capitol Police warned by FBI, NYPD of risk of violence at Capitol: report

3) 'Unacceptable!': Probe Demanded After Footage Shows Capitol Police Standing Aside for Pro-Trump Mob

4) Outgoing Capitol Police chief accuses House, Senate security officials of hindering efforts to call in National Guard

"Sund told The Washington Post in an interview published Sunday night – his first since the events at the Capitol Wednesday — that he asked House and Senate security officials in the days before Congress was set to count the Electoral College votes to allow him to request the D.C. National Guard to be on standby in case troops were needed ahead of the pro-Trump protests. 
 
 "But Sund, who was officially replaced as Capitol Police chief on Friday after his resignation, told tthe newspaper that the officials denied the request."

5) The FBI failed to give a "defensive briefing" to the Trump Campaign of possible foreign influence during the 2016 election while it gave such a briefing to the Clinton Campaign. (added 1/11/21)

6) Non-Trump supporters may have been present. (added 1/12/21)

7) McConnell is said to be pleased about impeachment, believing it will be easier to purge Trump from the G.O.P. (added 1/12/21)

8) FBI report warned of ‘war’ at Capitol, contradicting claims there was no indication of looming violence (compare with #2,4) (added 1/12/21)

9) FBI says there is ‘no indication’ that antifa took part in U.S. Capitol riot (added 1/13/21)

10) FBI director says antifa is an ideology, not an organization (added 1/13/21)

11) Dick Morris: Impeachment Goal: Ban Trump In 2024 (added 1/14/21) 

Connect these dots and tell me what you think.  If you have additional info that might change the conclusion, post a link.   

MARK LEVIN CONNECTED THE DOTS!

12) Mark Levin: There's No Evidence Of Trump Inciting An Insurrection (added 1/16/21)

The new bit of info from this monologue is that Trump and his Secret Service detail were never told of the likelihood of violence.  That would be consistent with #5 above to show a political motive (my opinion).


Thursday, April 30, 2020

Michael Moore Finally Gets Something Right!

I never thought I'd recommend anything presented by Michael Moore, but here it is! 

At 1 hour 40 minutes it is rather long for a You Tube documentary, but it is both compelling and informative.

While I disagree with the statement near the end that "we" are "destroying the planet" (because that varies with who, when, how and where) and the implications that we must have population control (a 50 year old idea discredited by time) and an end to capitalism (which has nothing to do with environmental protection) the effort  to expose at least some of the negative aspects of so-called "green energy" makes this a MUST SEE MOVIE!


Wednesday, April 15, 2020

Leading -- or Dictating?

According to WKTV last night: "MVHS MAY LOSE UP TO $31 MILLION AS CORONAVIRUS ATTACKS HOSPITAL REVENUES"

"The coronavirus could threaten the paychecks of the very frontline healthcare workers caring for the sick. Hospitals nationwide have had to furlough workers, in order to deal with a lack of elective surgeries, and subsequent loss of millions of dollars."

Why is there a lack of elective surgeries? On March 22, 2020, Governor Cuomo cancelled all elective surgeries in the state.

This financial mess is the Direct Result of the governor going way beyond his ken in determining that hospitals could not do "elective" surgeries.

What is "elective" vs "necessary" is both a matter of opinion and something that would change with the changing conditions/needs of a community. I don't think that a person with, e.g., a herniated disc would consider his operation "elective."

The decision of what procedures to allow should be left to the treating doctors and hospitals which are closest to the patients and what is happening in their communities. 

The president sent the hospital ship Comfort to NYC to assist the hospitals there to keep up with their non-Covid case load. However, because of the governor's edict, that ship sits empty, as are most hospitals across Upstate NY.

Empty hospital beds are a waste of resources. 

Simply put, the Covid-19 caseload is not here yet. Many of these "elective" patients will be in and out before that arrives.

The governor's actions have both prevented people from getting treatments that they need while imposing unacceptable and unnecessary financial burdens on hospitals and their staffs.

There is a difference between leading and dictating. This situation is the result of the latter.

Wednesday, November 20, 2019

Our Corruption is More Acceptable than Your Corruption . . . and Mr. Zlochevskiy's Brilliance ...

The Ukraine situation has become so controversial and complicated that timelines have been posted on-line to help the public understand the situation (or lead the public to a particular conclusion, depending on one's perspective).

I found a useful timeline posted at JustSecurity.Org and jotted down my thoughts (both on the situation and on the timeline's wording) to clarify things in my own mind. I only looked at the period from early 2014 through April 4, 2016, because that was enough to digest. Please look at the original timeline because my interpretation of events might be slightly different from theirs.

To set the stage: By March, 2014, under the Obama administration, Russia had invaded and annexed Ukrainian territory (the Crimea and portions of eastern Ukraine); Ukraine had a reputation as being a corrupt place; and  Burisma was Ukraine's largest private oil and gas extracting company. Mykola Zlochevskiy, who may be considered an oligarch, was Burisma's founder and majority shareholder.  He had also held various high-level Ukraine government posts.

April 2014:  The United Kingdom's Serious Fraud Office blocks the bank accounts of Mykola Zlochevskiy, who was suspected of corruption during the ousted pro-Russia Yanukovych regime. Under a commitment made to the Ukraine government  to recover assets allegedly stolen out of the country, the US had investigators work on the case against Mr. Zlochevskiy with Ukrainian investigators.

Also April 2014:  Hunter Biden, son of then-US Vice-President Joe Biden (who was the US "point man" on Ukraine policy),  "joins" Burisma's board of directors after having been discharged from the Navy just months earlier for testing positive for cocaine. Per Burisma Holdings, Hunter Biden was placed  “in charge of the Holdings’ legal unit ..."

  • "Joins?"  People don't just "join" a board - they are appointed by the shareholders.  And since Mr. Zlochevskiy was the majority shareholder, Mr. Zlochevskiy put Hunter Biden on his board.
  • Since US investigators were involved, why would Zlochevskiy's appointment of the then-VP's son NOT have a "chilling effect" on their desire to investigate Zlochevskiy?   

May - June 2014: Petro Poroshenko succeeds to the Ukrainian presidency following election on a platform of turning Ukraine back to the West.

August 2014: Ukrainian Prosecutor General Vitaly Yarema opens an investigation of  Zlochevskiy.

October 2014: Under pressure from the US and "other international backers," the Ukraine Parliament establishes the "National Anti-Corruption Bureau" (NABU) in exchange for financial aid.
  • Given the Ukraine's bad reputation, the US and "other international backers" had reason to be concerned that their aid might be frittered away by corruption. However, should it not be acknowledged that the insistence on NABU's creation  was, to some degree, dictating how Ukraine was to run its internal affairs?
February 2015:  Then US "senior anti-corruption coordinator" George Kent "scolded" a prosecutor from Yarema's office for having "shut the criminal case" against Zlochevsky.
  • Does the US scolding of a lower-level Ukrainian prosecutor, bother you?  
  • If you were that Ukranian prosecutor, would the fact that VP Biden's son continued as a high-level hire of Zlochevskiy send a conflicting message, at least insofar as an investigation of Zlochevskiy/Burisma is concerned?
Later in February 2015: Yarema was replaced by Viktor Shokin as Ukraine's Prosecutor General.
  • One prosecutor knocked off. Score one victory for Zlochevskiy.
September 24, 2015:  Then-US Ambassador to Ukraine Geoffrey Pyatt "as part of a regular drumbeat by U.S. and other Western leaders, including Vice President Biden," "excoriates" officials in then Shokin's office for "stymying anti-corruption investigations" and specifically called for the termination of officials who had sent letters to Zlochevskiy's attorneys attesting there was no case against him.
  • If a letter of "no case" was sent to Zlochevskiy's attorneys, would Hunter Biden, as a hire of Zlochevskiy in charge of Burisma Holdings' legal unit, have had some involvement with it? 
  • Do the US Ambassador's demand for termination of Ukraine officials, and his alleged interest in how the Zlochevsky case was handled, bother you as meddling in Ukraine's internal affairs? 
  • Again, did the fact that then-VP Biden's son continued as a high-level hire of Zlochevskiy send a message conflicting with VP Biden's public statements?
  • Score a second victory for Zlochevskiy in getting letters out of the Ukraine government stating Ukraine had no case against him.
October 8, 2015: Then-U.S. Assistant Secretary of State Victoria Nuland states that “the Prosecutor General’s Office (PGO) has to be reinvented as an institution that serves the citizens of Ukraine, rather than ripping them off ... including locking up dirty personnel in the PGO itself.”
  • Why/How is it Ms. Nuland's business to determine what "serves the citizens of Ukraine?"  Isn't that "the citizens of Ukraine" decision through their electoral process? At this point was the US 'helping' Ukraine combat corruption, or meddling in its internal affairs?
December 8, 2015: Then-VP Biden addresses the Ukraine Parliament, calling for reform of the Prosecutor General's office, arguing that "Oligarchs and non-oligarchs must play by the same rules," and noting the US' provision of hundreds of millions of dollars in aid to Ukraine.
  • Again, did the fact that then-VP Biden's son continued in the employ of and received pay from Zlochevsky, an oligarch, send a conflicting message? 
February 2016: Then-VP Biden pressures Ukrainian President Poroshenko to get rid of Prosecutor General Shokin, allegedly because Shokin was not pursuing corruption cases vigorously enough in the view of "virtually everyone" in US government "and other Western Nations," and that the US would not extend a $1Billion loan guarantee until Shokin was removed from office."JustSecurity.Org" notes that the investigation of Zlochevskiy's company had been "dormant," and that a "leading Ukrainian anti-corruption advocate" claimed that Shokin "didn't want to investigate Burisma" and was fired for that reason.
  • Why wouldn't  investigation of Zlochevskiy's Burisma lie dormant as long as Hunter Biden was in charge of its legal unit, and the then-VP Biden had apparent control over vital US aid to Ukraine? 
  • Would anyone in Ukraine's government want to risk the hundreds of millions in US aid cited by then-VP Biden by taking an action that could lead to his son losing an almost 7-figure-a-year job?
  • Score a third victory for Zlochevskiy in a second prosecutor getting fired.
On April 4, 2016: George Kent, then charge d'Affairs in Kiev wrote a letter to the Ukraine Deputy Prosecutor General  demanding that his office stop harassing entities and individuals with investigations based on their having been involved in US-supported anti-corruption projects. JustSecurity.Org claims that The Hill's John Solomon later "twists" this "to make it look like the Embassy was trying to suppress investigations."
  • But there were "investigations" being conducted by the PGO -- just not the ones desired by the then-US government.  Kent's letter, therefore, lends credence to Solomon's story that the last US administration did not want the "Anti-Corruption Action Centre" (Ant-AC) investigated. (Ant-AC is, apparently, a joint venture between various US officials spending US taxpayer money and George Soros.) 
  • While there was a US concern over "corruption" by Ukrainian oligarchs, the Ukrainians, via their then-duly elected government, seem to have had greater concern over corruption fostered by US and other foreign entities' meddling in Ukrainian affairs.  
To sum up:

The above timeline demonstrates that Mr. Zlochevskiy made a brilliant move by hiring the then-US VP's son for his company's board, because the "appearance of impropriety" was followed by (1) a lack of interest in investigating Zlochevskiy/Burisma and (2) essentially a letter of exoneration from the Ukranian government.  The fact that then-VP Biden did nothing to cure the "appearance of impropriety" (and there were many things that he could have easily done) speaks volumes.

The above timeline also demonstrates a shocking involvement of the then-US government and "other international backers" in the Ukraine's internal affairs, justifying the PGO's investigation of entities and individuals involved in US-supported "anti-corruption projects." 

The "cognitive dissonance" of US officials criticizing Ukraine for not going after Zlochevskiy/Burisma, while the then-VP's son continued in the employ of Zlochevskiy/Burisma, would be a potent distraction from what the Obama Administration plus "other international backers" were doing in Ukraine via the Ant-AC organization.

There is plenty that went on in the Ukraine, including actions by US officials - many of whom continued in office under the Trump administration, that needs investigating. 


Monday, January 21, 2019

Part IV. The SEQRA Process & Conclusion - Downtown Hospital DEIS

Comments on the Downtown Hospital Draft Environmental Impact Statement (Draft EIS).  The Applicant is Mohawk Valley Health System. The Project is the proposed Hospital. SEQRA is the State Environmental Quality Review Act.

Part IV. The SEQRA Process & Conclusion:

The SEQRA process is set forth in ENV Article 8 and its implementing regulatons, 6 NYCRR Part 617 (State Environmental Quality Review, SEQR). As described in the SEQR Handbook (p.3) :

    SEQR establishes a process to systematically consider environmental factors early in the planning stages of actions that are directly undertaken, funded or approved by local, regional and state agencies. By incorporating environmental review early in the planning stages, projects can be modified as needed to avoid adverse impacts on the environment.”

The availability of State funds for the Project was announced in early 2015, the site for the Project was announced in September, 2015, and we just got around to SEQR in 2018 when the Oneida County Industrial Development Agency made a Positive Declaration. Does that sound like “incorporating environmental review early in the planning stages” so that “projects can be modified as needed to avoid adverse impacts on the environment?” Why was SEQR not part of the planning of the Project from the very beginning, including the choice of the site? As noted under Part I Section I, the site of a project is an appropriate consideration under SEQR, and the State promulgated a non-exhaustive list of those actions considered to have significant adverse impacts (6 NYCRR 617.7(c)(1)). This could have been used to help screen or rank the sites – but it was not.

People may disagree with how the regulations were applied or sites ranked in Part III above, however, the process only took a few hours. This Project deserved at least that level of attention being paid to the environmental consequences of site selection. Most people would probably intuitively conclude that trying to shoehorn a hospital with acres of parking into the middle of a Central Business District that was built for another era, another style of development, and a different purpose would be more disruptive to the environment than locating the hospital on a site that had enough room and had been specifically designed for that use. It is no surprise that the choice of site is still a controversial topic after three years.

For a major project such as this, ENV 8-0109 requires preparation of an EIS. The regulations make clear that a government agency cannot undertake, fund or approve of an action until it has complied with the provisions of SEQR (see 6 NYCRR 617.3 (a)). But that is, in deed, what happened at least as far back as Summer 2016 when Oneida County put county employees, and Utica put city employees (the Planning Board’s Staff), to the task of engaging in regular meetings with MVHS to help plan for the Project at the Downtown Site, because government employee time is money.

If the applicability of SEQR and need for an EIS was not apparent to the local authorities at that point in time, then it should have been apparent when the County approved funding for MVEDGE to provide property appraisal services for MVHS aiding the pursuit of the Downtown Site. The County should have stopped further action and opened the SEQR process then, but it did not. Nothing was done about SEQR until there was an “application” that triggered a review – but, as noted above, the law wants the environment taken into consideration “early in the planning stages” so that “projects can be modified as needed to avoid adverse impacts on the environment.” Here, the County and City had employees planning this project without the environmental information required by law. It is a shame that so much time and money was spent on a flawed process.

Like the Site Selection Process appears to have been tainted by undue influence, the entire EIS appears tainted as well. People who have personally invested their time toward securing the Project for Downtown will have difficulty focusing on another site – an impossibility for those where the alternate site is in another jurisdiction.

At this point in time the Planning Board is faced with (1) an EIS that cannot support a SEQR finding because St. Luke’s appears to be the environmentally superior site and (2) having to give up jurisdiction because it has no legal authority in New Hartford.

The EIS must be rejected as inadequate, and the process reopened for a new Lead Agency to produce a revised Draft EIS that addresses all the open issues identified herein.

Friday, January 18, 2019

Part III. Matrix St. Luke’s Campus vs Downtown (using regulatory environmental criteria) - Downtown Hospital DEIS

Comments on the Downtown Hospital Draft Environmental Impact Statement (Draft EIS).  The Applicant is Mohawk Valley Health System. The Project is the proposed Hospital.

Part III. Matrix St. Luke’s Campus vs Downtown (using regulatory environmental criteria)
(Limited to these two sites because Applicant cannot be made to consider a site it does not own/have under option – see 6 NYCRR 617.9(b)(5)(v) (‘g’))






Summary Conclusion on Matrix:

Numerous adverse environmental impacts as identified by State regulation or law will be avoided or minimized by simply relocating the Project to the St. Luke’s Campus.


(continued)

Thursday, January 17, 2019

Part II. Relevant Environmental Concerns - Downtown Hospital DEIS

Comments on the Downtown Hospital Draft Environmental Impact Statement (Draft EIS).  The Applicant is Mohawk Valley Health System. The Project is the proposed Hospital.

II. Relevant Environmental Concerns

A. Impact on Land: This topic is addressed in Draft EIS Section 3.1. Exposure to impacted soils due to past urban use is recognized to be a concern. The EIS needs to acknowledge that this concern could be mitigated by Relocation of the Project to the St. Luke’s Campus due to the relative lack of prior development there.

B. Impact on Surface Water: This topic is addressed in Draft EIS Sections 3.2 (Surface Water) and 3.9 (Utilities). Section 3.2. acknowledges that segments of the Mohawk River and Barge Canal down gradient from the Downtown site have impaired water quality, that runoff from the site could impact surface water, and that certain measures can be employed to mitigate these impacts. The following issues remain to be addressed, however:

1.) Section 3.9 states that the new facility is expected to generate 187,000 gallons per day (gpd) of waste water; however, it also states that facility average water demand will be 500 gallons per minute (gpm), which equals 720,000 gpd. The 533,000 gpd difference between what is going into and what is coming out of the facility is unaccounted for, suggesting that the facility could potentially generate as much as 720,000 gpd (500 gpm) of waste water. Since that amount would be greater than the 360 gpm design flow that the local Publicly Owned Treatment Works (POTW) indicated it could accept (Draft EIS p3525/3527), there is a potential violation of the Clean Water Act that needs to be resolved.

2.) Assuming that the POTW has sufficient capacity to handle the wastewater from the facility, it is not clear from the Draft EIS that all the wastewater will reach the POTW due to the combined sewers and Combined Sewer Overflows (CSOs) that exist in the City of Utica. As noted above, the facility will be a significant new source of waste water in Utica. The route that the waste water will take from the facility to its ultimate disposition in the environment needs to be identified and traced. The illustration of the sanitary sewers proposed to serve the facility (Draft EIS p98/3527) does not show the ultimate disposition point. If the facility’s wastewater at any point flows past a CSO, some of it could end up in the River or Canal untreated, further impairing water quality, possibly causing a violation of the Clean Water Act, and/or leading to a reclassification of the CSO as an illegal Sanitary Sewer Overflow (SSO), which would lead to an environmental enforcement action against the City of Utica. The EIS needs to clairify where the wastewater will wind up and whether it would exacerbate water quality impairment.

3.) Given the recent demolition of the Tartan Textile Building to make way for the Nexus Sports Center, the sports-and-entertainment “U District” envisioned for the area next to the Auditorium and across Oriskany Boulevard from the Project site is no longer speculation. The potential generation of waste water and runoff from the U District needs to be examined with all the above as a Cumulative Impact.

4.) The Draft EIS fails to consider relocation of the Project to the St. Luke’s Campus as mitigation. (a) The number of patient beds will be close to those currently/historically on site, suggesting that the Project environmentally would be the replacement of an existing facility on site with no new impacts other than construction/demolition. (b) The federal wetland on-site naturally buffers surface water impacts. (c) Redirection of all sanitary waste flows through the Sauquoit Creek Pump Station will mean that no untreated waste will reach the River/Canal once current Consent Order work is completed. (d) There are no pending large projects near by that would cause cumulative impacts.

C. Impact on Groundwater: This topic is addressed in Draft EIS Section 3.3. The presence of impacted groundwater from prior industrial uses is mentioned as a concern. The EIS needs to acknowledge that this concern could be mitigated by Relocation of the Project to the St. Luke’s Campus, due to the lack of prior industrial uses there.

D. Impact on Flooding: This topic is inadequately addressed in Draft EIS Section 3.2.

1.) On July 1, 2017, significant flooding (causing abandonment of cars, risk to human life, and property damage) occurred on a newly reconstructed and re-opened section of the North-South Arterial and adjacent Lincoln Avenue in an area labeled “area of minimal flood hazard” on the federal map. Per media reports State DOT officials claimed that their drains worked properly but indicated there was insufficient capacity in the storm sewers or receiving stream to prevent the flooding from occurring. This flooding occurred approximately one half-mile from and at a higher elevation than the Project site. The Draft EIS mentions this event (p 57/3527) but fails to elaborate on it in spite of the concern being identified during Scoping. The Project description indicates that some existing storm sewers will be removed, some will be used, and others will be constructed. However, the Draft EIS fails to reveal whether the Project will depend upon any of the systems that were overwhelmed by the 7/1/17 storm. That information should be put in the final EIS.

2.) The Draft EIS acknowledges that full build out of the Project has the potential to increase stormwater runoff and exacerbate downgradient flooding during storms (p. 60/3527) but dismisses the issue with a statement that the Project will result in more pervious surfaces than now (implying less runoff). The Project’s acres of new, unbroken pavement are expected to have a different water retention characteristic and likely will be less able to retain/slow/infiltrate runoff than the existing patchwork of old/broken pavement, sidewalks, roofs, yards, etc. Whether or not flooding will actually occur cannot be known without calculations using surface characteristics, areas, and design storms. The EIS should use the rainfall pattern of the 7/1/17 storm to produce a hydrograph of the runoff, and use same to determine if the storm sewers and streams serving the Project site have the capacity to carry away the storm water to the Mohawk River/Canal without creating urban flooding.

3.) Runoff from the proposed “U-District” adjacent to the Downtown site must be addressed as a cumulative impact.

4.) The Draft EIS fails to consider relocation of the Project to the St. Luke’s Campus as mitigation. (a) The number of patient beds will be close to if not within those currently/historically on site, suggesting that the Project environmentally would be the replacement of an existing facility on site with no new impacts other than construction/demolition. (b) The wetland on-site is a natural flooding buffer. (c) The 7/1/17 storm caused no flooding at or near the St. Luke’s Campus. (d) There are no pending large projects near by that would cause cumulative impacts.

E. Impact on Air: This topic is addressed by the Draft EIS in Section 3.4.

1.) Fugitive emissions from regulated materials and impacted soils is acknowledged as a potential concern during construction (Draft EIS p. 67/3527). Relocation of the Project to the St. Luke’s Campus should be considered to mitigate this concern due to the lack of prior industrial uses at that location.

2.) The Draft EIS acknowledges that the Project’s road closures could increase emissions from mobile sources (p. 64/3527). Relocation of the Project to the St. Luke’s Campus should be considered to mitigate this concern because road closures would be unnecessary at the St. Luke’s Site.

F. Impact on Aesthetic Resources including Lighting: This topic is addressed by the Draft EIS in Section 3.5. It acknowledges the types of buildings currently on the Downtown site, that they will be replaced with more modern looking structures, and that the new structures will be consistent with the appearance of the renovated Utica Aud and what is planned at Harbor Point. However, the determination of appropriate aesthetics at the Downtown site has been standardized by the Gateway Historic Canal District Design Standards adopted in 2005. Although the Applicant acknowledged the existence of these standards in its CON application (i.e., noting a height limitation of 7 stories/70 feet on Draft EIS p. 373/3527), the Draft EIS failed to apply the standards. At 9 stories, the Project exceeds the acknowledged height standard making it an aesthetic impact requiring mitigation. This could be accomplished by:

1.) Redesigning the Project to conform to Gateway Historic Canal District Design Standards, or

2.) Relocating the Project to the St. Luke’s Campus where the standards do not apply and the building form is consistent with what is already on-site.

Another short-coming of the Draft EIS is the failure of its artist renderings to show the Project in context with surrounding buildings from important vantage points. Utica has a distinctive and unique skyline perhaps best appreciated driving south on Route 12 Arterial or east on Oriskany Boulevard. The Arterial/Oriskany Boulevard interchange is an important Gateway to Downtown. Travelling east on Oriskany Blvd. as one emerges from under the interchange, the skyline of Utica is revealed, ‘up close and personal’ on the right with prominent architectural examples such as the Adirondack Bank Building, Grace Church, State Office Building, new Bank of Utica clocktower, City Hall’s ‘Tower of Hope,’ and M&T Bank’s “Gold Dome” alternately coming into view. These buildings are also viewable as one travels south on Rt. 12 over the interchange. From either vantage point, the Project’s massive, lengthy, 9-story “slab,” out-of-scale with the neighborhood and street-grid, and placed across Cornelia St.,will block these views.



(From Google Maps. Eastbound Oriskany Blvd emerging from interchange. This viewshed is better appreciated in-person from different points while driving, without Google Map’s distorted perspective). 




(From Google Maps. Southbound Rt 12 passing over interchange. This viewshed is better
appreciated in-person from different points while driving, without Google Map’s distorted
perspective).


G. Impact on Historic and Archeological Resources: This topic is addressed by the Draft EIS
in Section 3.6 as well as in Appendices E and H. The Draft EIS acknowledges and extensively
documents the existence of sites of Historic or Archeological significance within the
Downtown site
which may be disturbed/destroyed/adversely affected by the Project, including
sites on the National Registry, sites eligible for the National Registry, sites listed in the Downtown Genesee St. Historic District, and sites related to operation of the Erie/Chenango Canals. The
Draft EIS postpones definition of mitigation measures pending further study, consultation with,
and action by OPRHP to prescribe measures to mitigate impacts to known and unknown historic
properties; but anticipates such measures to include further assessments/testing of properties,
etc. (which might be characterized as documenting what is there and saving some artifacts
before structures are destroyed). The Draft EIS needs to acknowledge that impacts to Historic
and Archeological Resources may be avoided by relocating the Project to the St. Luke’s
Campus. 


H. Impact to Transportation: This topic is addressed by the Draft EIS in Section 3.7. It
acknowledges various potential construction and operational traffic impacts, describes current
streets, presents current and anticipated traffic Levels of Service (LOS) for various intersections,
and proposes forms of mitigation.

1.) As detailed in the Draft EIS (pp 90-91/3527) the Project will cause a deterioration in
LOS for several intersections (i.e., the Project will cause unacceptable traffic delays at
certain intersections for certain movements according to the ratings). Although changes to
signals etc. are proposed as mitigation, no evidence is presented to demonstrate that
these will decrease the delays or otherwise improve LOS. Therefore, there is an
unavoidable adverse impact to traffic.

2.) What the traffic analysis methodology, and the minutiae it generated, failed to
capture – and what the EIS must acknowledge – is the broader concept of a Street
Grid -- that the Project will destroy a portion of the Grid, and that this could have
unintended and unpredictable social, economic, health and environmental
consequences.

Like the honey-comb structure of a hive serves the purposes of bees, street grids are a
tried-and-true method of organizing the urban environment for human efficiency, which go
back millennia. The raison-d’etre of cities is to permit humans to be in close proximity to
and interact with each other. Street grids promote that interaction by organizing human
movements into predictable patterns and giving persons access to each other. Disrupting
the grid disorients travel, creates barriers to movement, and has the effect of increasing
the distance between people -- undermining the purpose of city existence. Places once
easily accessible become hard to reach, lessening their usefulness. A two block trip
becomes four – or more. An easily missed turn becomes an opportunity lost when a
customer can no longer simply go around the block. More energy than necessary is
expended, and more pollution is created.

The Draft EIS (pp.83-4/3527) recognizes that Lafayette and Columbia Sts. are urban
major collector streets which connect places outside the study area. The EIS needs to
acknowledge that they both run generally east-west and are parallel and redundant to
each other as part of a grid. Redundancy is a benefit of the grid best appreciated when a
street is temporarily blocked, but one can go around the blockage by moving over one
block. This is a common occurrence on Columbia St. by delivery trucks, easily managed
by using Lafayette St. instead. When the hospital permanently closes blocks of Lafayette
St., the redundancy will be lost.

Cornelia St. runs roughly north-south, roughly parallel and redundant to Broadway. Both
give access from Court St. to Whitesboro St. and the Baggs Square W. neighborhood near
the Auditorium. The Project will close a portion of Cornelia St., limiting access from Court
St. to Baggs Sq. W. to only via Broadway.

Temporary blockages due to deliveries, stalled trucks, fires, burst water mains, cultural
and sporting events, etc., are a common fact of City life. They are unpredictable and
not accounted for in the traffic studies. What is predictable is that the Project’s street
closures will make it more difficult for people, and City authorities, to deal with
them. The EIS must acknowledge that the Project’s street closures will turn what are now
minor inconveniences into potential gridlock. Disruption of the street grid is, per se, an
unmitigatable adverse impact to transportation.

3.) The Draft EIS fails to address the Cumulative Impacts of the Project with the
NYSDOT’s Route 5S work. After the State closes the Washington and Seneca Sts.
crossings of Oriskany Blvd., and the Project closes Cornelia, how would one access
Baggs Sq. W from Court St. if Broadway were to become temporarily blocked?

4.) The Parking demand appears overstated and the ITE methodology not explained, not
readily available to the public, and likely misapplied given gross differences between the
Project and hospitals elsewhere, cited during Scoping (Draft EIS pp1032-3/3527). How
does the proposed parking compare with Applicant’s current use (which should be
conservative given scale-back in Applicant’s operations)?

5.) The EIS must recognize that the traffic impacts identified above would be
avoided by Relocating the Project to the St. Luke’s Campus where (a) the negligible
increase in bed-capacity on site would produce a negligible increases in traffic and parking
demand (b) no public street would have to be closed and (c) there is nothing pending to
suggest a Cumulative Impact to traffic.

I. Impact on Energy: The Draft EIS addresses this topic in Sections 3.8 and 4. The Draft EIS
acknowledges that to service the Project, existing electric and natural gas infrastructure will be
relocated out of the IHC footprint, into public rights-of-way (p.93/3527). It also acknowledges that
to meet demand and minimize disturbances to existing customers, an 80 psi, 6-inch diameter gas
main would be installed and extended approximately 2,500 lf to the site from National Grid’s
existing 80 psi supply main, and that extension of the gas main may require crossing underneath
an existing railroad. (p.94/3527). The Draft EIS indicated that construction would be in
accordance with applicable codes to minimize impacts.

1.) In spite of being raised twice during Scoping (pp. 1035 &1438/3527), the Draft EIS fails
to disclose and needs to acknowledge the impact of the Project on the Co-Generation Facility recently constructed on the St. Luke’s Campus that is shared between St.
Luke’s facilities and Utica College.
The Hospital is the only customer for hot water and
steam, and the largest customer for electricity. The facility’s use numbers make it appear
that this community resource, which contributes to the resiliency and efficiency of the
energy system, would have to close if the hospital were to be moved to the Downtown site.

2.) Placing the Project Downtown deprives Applicant of the energy-efficiency of the Co-
Gen facility and undercuts Applicant’s sustainability.

3.)The Draft EIS fails to discuss Cumulative Impacts to Energy from anticipated “U-District”
projects.

4.) Given the acknowledged impacts to off-site locations, public rights of way, potential “UDistrict”
Cumulative Impacts, and the Co-Gen questions, the EIS needs to discuss
whether such impacts could be avoided or lessened by relocating the Project to the St.
Luke’s Campus given the Co-Gen facility being on said campus and no “U-District” nearby.

J. Impact on Utilities: The Draft EIS addresses this topic in Section 3.9. It acknowledges that
existing sanitary sewers, water lines, storm sewers would be removed and replaced with new
pipes and arrangements, impacts would occur from this work, and that some of this work would
be in public rights of way just off-site.

1.) The Draft EIS fails to acknowledge that the existing facilities are a grid that developed
to serve a small-scale incremental type of development; that there is an increasing
demand for this type of environment for redevelopment in Utica (e.g. recent Baggs. Sq.
redevelopment); that such redevelopment is of the type intended to be fostered by the
Gateway Historic Canal District rules and the Utica Master Plan; and that destroying this
grid would be the waste of a community resource needed to foster redevelopment.


2.) The Draft EIS fails to address Cumulative Impacts from the “U-District” on utilities.

3.) The Draft EIS fails to acknowledge that the above impacts could be largely avoided by
relocation of the Project to the St. Luke’s Campus where the public grid would not be
disturbed.

K. Impact on Noise and Odor: The Draft EIS addresses this topic in Section 3.10. Impacts are
expected to be primarily related to the construction phase. The Draft EIS fails to acknowledge
that relocating the Project to the St. Luke’s Campus would minimize these impacts, particularly to
off-site receptors, owing to the Campus’ more-open surroundings, the decreased need to
demolish buildings and reroute public infrastructure, and the likelihood that such impacts would
be better monitored by an on-site Applicant.

L. Impact on Human Health: The Draft EIS addresses this topic in Section 3.11. The Draft EIS
acknowledges that impacts to health could result during the demolition and construction phases
through exposures to impacted soils and groundwater and hazardous materials, such as
asbestos from old buildings. The Draft EIS touts the health purposes of the Project without
reference to site, and attempts to address the “red zone” railroad problem.

1.) The Draft EIS fails to consider that the purposes of the State’s Grant – which is
intended to improve human health – are undermined by the Project’s placement on
the Downtown Site
, as opposed to the St. Luke’s Campus, because: (a) it dis-integrates
the system of care by placing 2 miles between the new hospital beds and the rehab/nursing facility, (b) removes the anchor institution from the existent defacto medical district near the Utica/New Hartford line, (c) gives the Applicant an additional medical campus to manage; and, apparently, per the Applicant’s own numbers, (d) undermines Applicant’s financial stability by increasing the number of staff per hospital bed. (See Part I above).

2.) The Draft EIS makes clear that placement of the Project Downtown places it in a traffic
area where delays will be exacerbated by the Project’s own traffic and street closures.
Additionally, because the streets to be closed are part of a grid, common blockages which
now cause inconvenience could post-Project cause gridlock, making hospital access
difficult and life threatening. (See Section H above).

3.) With regard to the “red zone” reference is made to my prior Scoping comments on this
topic (Draft EIS p. 1036/3537). Although the Draft EIS attempts to address concerns
raised during Scoping about the potential of having to evacuate the Project were a train
derailment to occur involving hazardous substances on the CSX Railroad Tracks which
pass about 900 feet north of the project site, the Draft EIS still fails to assess the
feasibility of evacuating what would become Greater Utica’s only hospital and fails
to substantiate any feasibility with an Evacuation Plan.
This should have been a “fatal
flaw” of the Downtown Site.

WARNING: The City of Utica, County of Oneida and other involved agencies are
hereby placed on notice that if they approve of this Project on the Downtown Site,
they are knowingly and unnecessarily placing human lives at risk both due to
gridlock and the red zone because the St. Luke’s Campus does not carry such risks.


M. Consistency with Community Character and Plans: The Draft EIS addresses this topic in
Section 3.12. Its approach is to ignore the word “Plans.” Reference is made to my prior Scoping
comments on this topic (Draft EIS p. 1036-7/3537) since they were disregarded.
 

1.) The Project is inconsistent with the Gateway Historic Canal District’s plan and
building-form rules
(see e.g., Draft EIS p. 373/3527), which were Council-approved in
2005. The Draft EIS fails to disclose that the Downtown Site lies within the said District
(an area bounded by Genesee, State and Columbia Streets and the CSX Tracks).
 

2.) The Project is inconsistent with the Utica Master Plan, approved by the Council in
2011 and updated in 2016. This and the Canal District plan envision mixed uses and
“walkability” Downtown, not a Medical Campus of a few massive buildings surrounded by
acres of parking.
 

3.) The Project’s street closures are inconsistent with Utica’s Street Plan, compiled
incrementally over Utica’s history by City ordinances.
 

Per 6 NYCRR 617.7(c)(1)(iv), the material conflicts above are per se a substantive and
significant adverse environmental impact that either must be mitigated or avoided. The
DEIS fails to propose either. Relocation of the Project to the St. Luke’s Campus would
avoid these inconsistencies.


 N. Impacts on Solid Waste Management: The Draft EIS addresses this topic in Section 3.13.
It acknowledges possible impacts during the construction phase from disposal of impacted soils
and groundwater and hazardous building materials among the Construction and Demolition
debris. With a decreased need to demolish buildings with unknown hazards and an historically
less-impacted site, relocation the Project to the St. Luke’s Campus should be considered in
mitigation of this environmental impact.


O. Environmental Justice:
The Draft EIS acknowledges the need to address Environmental
Justice in Section 1.2.3 and in several other places, mentions several times that the Downtown
Site is potentially an Environmental Justice area, but then fails to offer anything about the
issue.
The Draft EIS fails to assess the Project’s impacts on the protected population or
otherwise deal with those impacts
. In this regard it is noted that the Project will displace from
the neighborhood, if not destroy, about 40 business and other entities where people are working.
No attempt has been made to assess the number or holders of those jobs, their circumstances,
or whether they are members of the protected population. The Project will also displace or impact
several charitable institutions that serve the protected population, such as the Salvation Army
and Compassion Coalition. Jobs and services clearly are going to be lost to the neighborhood.
The EIS must acknowledge that Environmental Justice impacts may be completely
avoided by relocation of the Project to the St. Luke’s Campus, which is not in an E-J
neighborhood.


P. Cumulative Impacts: The Draft EIS addresses this in Section 5, out of context with the areas
of environmental concern and with little information. It dismisses the “U-District” as “speculative,”
when it is not, considering that a building has already been demolished in preparation and its
frequent coverage in the press. The referenced CSO project only tells us what it is but has yet to
be placed into context with this Project because the EIS lacks information on the routing of
Project waste water, as already pointed out. Cumulative Impacts need to be addressed under
each relevant area of environmental concern.
 

Relocation of the Project to the St. Luke’s Campus must also be considered in the EIS in
mitigation of Cumulative Impacts as there are no known large-scale projects in its vicinity that
could impact the Project.
 

Q. Creation of a Demand for Other Actions that Could Impact the Environment: This topic
is only partially touched upon in the Draft EIS in Section 8.2 “Adaptive Reuse of FSLH and
SEMC,” and is otherwise ignored.


1.) The Project will take the new Utica Police Garage, disrupting the Utica Police Campus
which also includes the Police Station, Utica City Court, and associated parking. No plan
for the garage’s functions has been announced, and the impact on the functioning of the
other portions of the Campus is unassessed. The change in the map of the Utica Police
Campus suggests that it will be ‘squeezed out’ by the surrounding Medical Campus, and
create a need to build a new Police Campus (Garage, Station and City Court) elsewhere.


2.) The Project will take the facilities of some 40 business and other entities, and likely
force others out of the neighborhood due to construction disruptions. If these entities
continue their existence elsewhere they likely will go to the suburbs (Empire Bath has
already moved to Marcy, and Brandeis will be moving to Whitesboro). Forcing businesses
out of the City creates sprawl, increasing the demand for public infrastructure and
services, making the public more dependent on the automobile, and wasting energy.
 

3.) The Draft EIS deals with the future of the St. Luke’s and St. Elizabeth’s Campuses by
‘kicking the can down the road’ – i.e. reuse of facilities to be abandoned is still being
studied. Given the sizes of each campus any use change is likely to have a significant
impact on their respective neighborhood, and would be impacts of the Project because the
Project is causing the abandonment. The Draft EIS’ vagueness is unacceptable in a
community that has had to deal for over 20 years with the blight caused by the State’s
abandonment of hospital facilities on the Psychiatric Center Campus. One building has
only recently been leveled after years of broken windows. The multistory, hulking Brigham
Building still sits empty on the corner of Noyes and York Streets, dragging on the
neighborhood. Simply put, there does not appear to be any market for abandoned hospital
buildings, so “adaptive reuse” of these facilities sounds speculative. The EIS must
propose mitigation measures that assure that Applicant’s abandonment of facilities will not
create new blight in South Utica and New Hartford. As mitigation, consideration should be
given to requiring Applicant to post a performance bond to fund continued maintenance
and/or demolition of abandoned facilities, if they are not repurposed within an appropriate
specified time period.
 

4.) Relocation of the Project to the St. Luke’s Campus should be considered in mitigation
of potential demands for other actions because: (a) there would be no need to disrupt the
Utica Police Campus, (b) there would be no need to displace businesses and others, and
(c) some of the St. Luke’s facilities could continue to be used to serve the Applicant (e.g.,
the Medical Office Building and the Co-Gen Facility).


R. Smart Growth Policy (Environmental Conservation Law Article 6): The Draft EIS makes
some references to the State’s Smart Growth Policy (pp. 48, 49, 1591/3527) regarding the Site
Selection Process, but otherwise ignores the subject. The Draft EIS claims that the Downtown
Site would be viewed more favorably if state funds are pursued and that re-purposing urban
parcels is a sustainable initiative. The Draft EIS assigns extra “points” to the Downtown Site as
being “smart growth.” However, the Draft EIS’ treatment of the topic is absurd -- like a box to be
checked – without any apparent understanding that the purpose of the law is to minimize sprawl.
The Project exacerbates sprawl by: (1) ripping out (wasting) an urban grid infrastructure and
replacing it with a suburban-style campus with acres of parking (a low level use); (2) wasting
Applicant’s existing suburban campus, unnecessarily dispersing Applicant’s facilities; and (3)
pushing out 40 entities currently occupying the Downtown Site, and likely driving many of them to
the suburbs or lesser developed areas. Simply, the Draft EIS turns the State’s Smart Growth
Policy on its head. The EIS needs to acknowledge that relocating the Project to the St.
Luke’s Campus would be more consistent with Smart Growth principles because it avoids
the three negatives listed above. 


S. Unavoidable Adverse Environmental Impacts: The Draft EIS addresses this topic in Section
6. It relates several short term impacts arising from construction, and several long-term impacts,
specifically (1) demolition of existing buildings within the project footprint (including relocation of
existing businesses), (2) new traffic patterns due to permanent closure of existing roads (3)
periodic noise events from emergency helicopter access/egress and (4) modified viewshed. The
language chosen hides the significance of the unavoidable impacts. For example, “change in
traffic patterns” neither reflects the decline in traffic LOS at key intersections, nor the destruction
of important redundancy in the Street Grid as discussed at H above. The Draft EIS fails to
acknowledge that the nature and significance of these impacts are tied to the site chosen,
and that these short and long-term impacts could be minimized or entirely avoided by
relocating the Project to the St. Luke’s Campus.

 
T. Irreversible and Irretrievable Commitment of Resources: The Draft EIS addresses this
topic in Section 7. The wording used attempts to minimize the significance of what will be lost.
The EIS needs to acknowledge that a grid of public infrastructure (streets, sidewalks,
sewers, utilities) that can support the kind of private, taxpaying, incremental
redevelopment of Utica that is contemplated by the City’s official plans will be irretrievably
lost.
The new Police Garage will be taken. Numerous existing businesses with their associated
jobs, income and the personal wealth of their owners will be lost. Utica will lose perhaps its best
site (as part of the Central Business District) for business startups and growth, especially at a
time that the immediately adjoining areas (Baggs Sq. and Varick St.) are becoming filled. The
property and sales taxes generated here will be lost. While the Draft EIS in its next section paints
a pie-in-the-sky picture of a future filled with economic development, reality is that the hospital
and its parking facilities will take over the very places where economic development
would occur, and destroy the personal wealth of the very entrepreneurs positioned to
make it happen
, the ones in business there now, as history of urban renewal projects in Utica
has shown.


The EIS should also make the same analysis for the St. Luke’s Campus. It would
undoubtedly conclude that relocating the Project to that site would minimize irreversible and
irretrievable commitment of resources.
 

U. Growth Inducing Aspects: The Draft EIS addresses this topic in Section 8 with a lot of
forward looking rosy assumptions including tax figures based on smoke-and-mirrors. There is
practically no substantive evidence, much less than a reasoned elaboration, to back up the
claims.


As requested during Scoping (Draft EIS p. 1038/3527), this section of the EIS should include
consideration of “negative growth”
with associated adverse impacts (the spread of blight
and the wasting of community resources).
 

Currently available information suggests that the Project, when completed, will exacerbate the
region’s negative population trends through the destruction of jobs.
Hospital jobs will be
reduced by at least 184 (Draft EIS pp589-90/3527, if the Applcant’s numbers are believed), due
to the reduction in authorized hospital beds from 571 to 373 (see the NYS Department of Health's
Needs Analysis). Most non-hospital jobs (with no attempt to even count them in the Draft EIS)
associated with the approximately 40 entities currently within the Downtown hospital site will disappear based upon the 90%+ closure rate experienced by Rome, NY businesses previously in
the footprint of its Ft. Stanwix urban renewal project. The Project’s occupation of 25 Central
Business District Acres
, primarily for parking, not only will remove this acreage from private
development but also
drive up the cost of remaining CBD property by restricting supply.  That will discourage new startups and the creation of new jobs. Meanwhile the City of Utica will
be burdened with providing municipal services to new facilities that do not generate taxes, raising
taxes for everyone else and making Utica less attractive for investment.
 

Simply put, the Project will replace an urban neighborhood that contributes to its upkeep
with suburban sprawl that will not. The EIS needs to not only address these concerns but
also acknowledge that they could be minimized by placing the new facility on the St.
Luke’s Campus.
 

V. Conclusion re Environmental Concerns
 

Significant environmental concerns are either ignored, understated, or masked by a focus
on minutae.
 


(continued)